West Main Street Update

The West Main project will not be completed for about another 2 weeks. There are 5 connections that must still be accomplished, including the courthouse, two of which require installation of vaults that have not been received. Unfortunately, the contractor, while hoping to be complete by the end of March, has a contract that gives him 150 days or until the end of April to complete.

Recent Posts

Notice of Judicial Sale

September 22, 2023

Randolph Ave Water Line Replacement Update

September 20, 2023

Randolph Ave Water Line Replacement Update

September 6, 2023

Important Tax Reminder

September 1, 2023

Randolph Ave Water Line Replacement Nearing Completion

August 31, 2023

Important Changes to Utility Payment Options

August 25, 2023

Hazard Mitigation Plan Update

August 25, 2023

Speed Limit Change for Rt. 99.

August 22, 2023

Robinson Tract Water Project - Resident Notice

July 24, 2023

Independence Day Closings & Garbage Collection

June 26, 2023

Changes to Two-Way Traffic Pattern

May 16, 2023

Main Street to be Opened to Two-Way Traffic

April 27, 2023

Randolph Ave Water Line Replacement

April 5, 2023

Randolph Ave Paving

March 31, 2023

West Main Street Update

March 31, 2023